C2 Terminal Ineos Oxide, Antwerp, BE
Delivery and construction of a pipe rack and various supporting structures and stairs, including a platform next to/ attached to a tank.
- ClientTGE Germany, for Ineos, Antwerp
- Weight800 tonnes of steel
- Our activities includeDetail engineering, production and installation of:
Stairs, pipe rack and cage ladder to the liquid-gas storage tank
Platform and catwalk on the liquid-gas storage tank
Platforms for equipment
Pipe racks
- Start of workMay 2011
- Start of constructionJune 2011
- Completion of phase 1 (98%)December 2011
- Completion of phase 2 (2%)May 2012